SITE GROUP
EG MALL Azman: 2nd floor. TB2. Request for M&E slab inspection. At 3pm. 2nd floor, zone TB2.
EG MALL Azman: 2nd floor. TB2. M&E inspection done. @Mr. Voo
NSC GROUP
EG MALL Azman: Good morning.
Site progress photo.
29/08/2023.
6th floor. TB1. Slab rebar and M&E in progress.
EG MALL Azman: 2nd floor. TB2. Slab rebar and M&E in progress.
EG MALL Azman: 6th floor. Zone 4. Column rebar in progress.
EG MALL Azman: 6th floor. Zone 5a/5b. Lift formwork in progress.
EG MALL Azman: 4th floor. Slab formwork and 3rd floor lift rebar in progress.
EG MALL Azman: Ground floor. TB3. Skab formwork in progress.
EG MALL Azman: 4th floor. Zone 6. Slab formwork in progress.
EG MALL Azman: 6th floor. TB1. Slab rebar and M&E in progress.
EG MALL Azman: Please be inform. Today M&E meeting postponed to next week due to slab inspection. If there is any issue to discuss please inform me at the site. Tq.
EG MALL Azman: 2nd floor. TB2. Slab rebar and M&E in progress.
Dart Econmech: Hi. Mr Raymong. Tomorrow got site meeting? Or replace to another day?
EG MALL Azman: Please be inform. SITE MEETING, Tomorrow 30 August, Wednesday at 10.30am.
+60 16-833 5519: Bukan 3pm??
+60 16-833 5519: Ok noted…
EG MALL Azman: 10.30am. Pagi. Info dari Konsultan
+60 16-833 5519: Ok boleh…
No comments:
Post a Comment