Site progress photo.
28/08/2023. 6th floor. TB1. Slab rebar in progress.
EG MALL Azman: 2nd floor. TB2. Slab rebar in progress.
EG MALL Azman: Basement. Zone 9a. Slab cast.
EG MALL Azman: 3rd floor. TA1. Lift wall rebar in progress. 4th floor. Slab formwork in progress.
EG MALL Azman: 6th floor. Zone 4. Column rebar in progress.
EG MALL Azman: 6th floor. Ozone 5. Lift wall and column rebar in progress.
EG MALL Azman: 4th floor. Zone 6. Slab formwork in progress.
EG MALL Azman: Basement. Slab foundation
EG MALL Azman: Basement, slab foundation.
EG MALL Azman: @~Leppong clearing untuk pasang besi in progress sda ya. 🙏💪💪💪
EG MALL Azman: 1st floor. Toilet area. Plastering in progress.
+60 17-866 0355: Ok man
+60 14-379 2990: @EG MALL Azman tolong inform, frame pintu perlu relocate..kami cat pipe.. GL :GF E-F/8-9
+60 14-379 2990: Tq man.. 🙏🏻
EG MALL Azman: Ground floor toilet. Brickwall in progress.
EG MALL Azman: 5th floor. ST7. Staircase rebar in progress.
+60 17-866 0355: 5th floor st 7 staircase done
+60 17-866 0355: Man tolong bagi tau GNB kasi pinda ni besi tidak boleh pasang conduit
EG MALL Azman: Ok bal. Sda info GnB.
EG MALL Azman: 2nd floor. TB2. Slab rebar, M&E in progress.
Lo. W. H (HKL-Site Engineer): dear all valued NSC, attached herewith the 7th floor archi plan
Lo. W. H (HKL-Site Engineer): Rwdp lagi