SITE GROUP
EG MALL Azman: @Kadapi J. PROMES ground floor, zone TA1. Slab rebar and electrical conduit still in progress. We request you to standby onsite for inspection after all the services are installed. 🙏🙏.
Kadapi J. PROMES: Top layer bar installation still in progress
NSC GROUP
EG MALL Azman: Morning. Today Survey Bos will come visit the site. All subcon please keep housekeeping in your work area. Thank you 🙏.
EG MALL Azman: Morning. @Leung KH🍀 @Edwin Chen 013 . We are in progress covering the soil next to the wall. Please close this pipe outlet well so that water does not enter through it from outside later. Thanks. 🙏🙏🙏
EG MALL Azman: St08 5-6f rebar
+60 17-866 0355: man hari ni kongkrit ka
EG MALL Azman: Iya. Cast plan ni hari.. itu kawasan belum bottom rebar saya push subcon supaya NSC boleh start pasang sana. 🙏💪💪💪💪💪
EG MALL Azman: Site progress photo.
25/08/23
6th floor. Zone 4. Slab cast.
EG MALL Azman: 6th floor. 5a. Lift wall formwork.
EG MALL Azman: 6th floor. 5b. ST8 rebar in progress
EG MALL Azman: 4th floor. TA1. Slab formwork in progress. 3rd floor. Lift wall formwork in progress.
EG MALL Azman: 6th floor. TB1. Slab formwork in progress.
EG MALL Azman: 4th floor. Zone 6. Slab formwork and scaffolding in progress.
EG MALL Azman: Ground floor. TA3. Slab rebar & M&E in progress.
EG MALL Azman: TB2. 2nd floor formwork in progress.
60 17-866 0355: M&E inspection ground floor