Azman HKL: Latest casting plan. Please take note.
Azman HKL: Morning.
21/08/2023.
Site progress photo.
3rd floor. TA1. Slab cast.
Azman HKL: 6th floor. 5a/5b. Slab rebar and M&E in progress.
Azman HKL: 6th floor. Zone 4. Slab rebar in progress.
Azman HKL: 6th floor. TB1. Slab formwork and scaffolding support in progress.
Azman HKL: Ground floor. TA3. Slab formwork in progress.
Azman HKL: Basement earthwork in progress.
Azman HKL: 3rd floor. Zone 6. Column and luft formwork in progress. 4th floor slab scaffolding in progress.
Azman HKL: @Azman HKL ni Staircase ada M&E ka? Esok mau tuang simen
Azman HKL: Please take note. Tolong double check services ya.
+60 17-866 0355: Ok man
Azman HKL: 6th floor. 5b. Slab work progress early from schedule. Casting plans change to today as per discussion on site. Please take note. Any obstruction. Please inform me early. πππ.πͺπͺ
Azman HKL: M&E inspection schedule to 3pm in the afternoon.
Azman HKL: Slab cast postponed tomorrow due to rain.
Raymond Chong. Y. F (HKL P. Manager): @Azman HKL pintu genset room sudah pasang ka?
Azman HKL: Sudah pasang pintu bos.