Azman HKL: 3rd floor. TA1. Slab. M&E services in progress. Cast plan on 20/8/23 tomorrow.
Azman HKL: 3rd floor. Zone TA1. @Kadapi J. PROMES Request for inspection. Tomorrow morning. @~. @~Walker Yapi @Leung KH🍀 please make sure check and all services ready for tomorrow inspection and casting.
NSC GROUP
Azman HKL: Site progress photo.
19/08/2023.
3rd floor. TA1. Slab formwork, rebar and M&E in progress.
Azman HKL: 6th floor. 5a/5b. Slab/beam rebar, lift wall formwork in progress.
Azman HKL: 3rd floor. Zone 6. Column rebar/formwork, lift wall rebar parapet wall rebar in progress.
Azman HKL: 6th floor. Slab formwork in progress.
Azman HKL: 6th floor. Zone 4. Slab formwork in progress.
Azman HKL: 1st floor. TB2. Column rebar in progress.
Azman HKL: Ground floor. TA3. Slab formwork in progress.
Azman HKL: 3rd floor. TA1. M&E services on slab in progress.
Azman HKL: @Jimmy HKL @Tolong kasi tau semua subcon jangan ambil sy punya plywood hollow dan scffollting buat tidur
Azman HKL: @~. @~Leppong @~Walker Yapi tolong cek ya siapa yang pasang begini. Kalau ada, tolong elakkan la.
+60 17-866 0355: Ini bukan kami yang pasang. Org GnB juga yang pasang situ. Tempat rehat dia org.
+60 17-866 0355: Ini semua pekerja mereka yang pasang. Banyak lagi di atas.
Azman HKL: 😩 ok.. tolong sajala ya. Nanti saya inform dia org.