Thursday, August 17, 2023

18 AUG 23 HKL

 

NSC GROUP

 Raymond Chong. Y. F (HKL P. Manager): @Azman HKL ni motor belum pindah lagi, keja korea datang hackking
Raymond Chong. Y. F (HKL P. Manager): King Hong👆
Leung KH🍀: Good morning boss , noted


Raymond Chong. Y. F (HKL P. Manager): Thanks
 Azman HKL: @Leung KH🍀 kasi pindah ini pagi..
 Azman HKL: 6th floor. 5a/5b. Slab beam, lift wall formwork in progress.
 Azman HKL: 6th floor. Zone 4. Slab formwork in progress.
 Azman HKL: 6th floor. TB1. Slab scaffolding/formwork & column rebar in progress
 Azman HKL: 3rd floor. TA1. Slab formwork/rebar and M&E in progress.
Azman HKL: Ground floor. TA3. Slab formwork in progress.
Azman HKL: 1st floor. TB2. Column rebar in progress.
 Azman HKL: 3rd floor. Lift wall rebar, column rebar, parapet wall in progress.
Azman HKL: Itu ground floor lantai maw hack sda. Apa2 barang di bawah kasi pindah dia sekarang supaya barang tidak rosak.
 Raymond Chong. Y. F (HKL P. Manager): Econmech, how big your store?
Raymond Chong. Y. F (HKL P. Manager): suggest u make G/L G-H/9-10 as your store at GF
[09:08, 18/08/2023] Dart Econmech: Wait ya
Raymond Chong. Y. F (HKL P. Manager): try not too closed to the columns, make it at the centre of 4 columns
 Dart Econmech: Ok can
 Raymond Chong. Y. F (HKL P. Manager): here ya
Dart Econmech: Ok tq mr raymond. Need to remove some brick. Will coordinate at site
Raymond Chong. Y. F (HKL P. Manager): 👌


Azman HKL: -Hacking brick wall install PVC conduit.. 
kasi jelas dia.  👆