NSC GROUP
Azman HKL: Site progress picture.
15/08/23.
5th floor. TB1. Slab cast.
Azman HKL: 3rd floor. Zone 6. Slab cast.
Azman HKL: 3rd floor. TA1. Slab formwork in progress
Azman HKL: 6th floor. Zone 4. Slab formwork in progress
Azman HKL: 6th floor. 5a/5b. Slab formwork in progress. Column rebar in progress. Lift wall formwork in progress.
Azman HKL: 1st floor. TB2. Column rebar in progress.
Azman HKL: Ground floor. TB3. Slab formwork in progress. Basement staircase rebar in progress.
Azman HKL: Basement. Slab foundation in progress.
Azman HKL: Basement. 8d. Slab foundation work.
Azman HKL: Reminder
After work, please make sure to do housekeeping at work especially hacking work. Keep the good work all the time. Thanks.. 👍😊👍
KH Karen: Good afternoon, our materials will arrive eg mall site by early next week, exact date to be confirmed.
2 units of 40FCL with 5 FRP tanks and 4 grease interceptors.
Azman HKL: Thanks for the info. Noted. @Leung KH🍀 later we discuss lifting method and storage on site.. 👆
Leung KH🍀: Ok bro , tq🙏🏻
+60 17-866 0355: M&E done