Friday, August 11, 2023

11 AUG 23 HKL

NSC GROUP
Azman HKL: Casting plan update

2) Zone TB2 1st Floor - 14/8/23 - isnin

3) Zone 6. 3rd Floor - 11/8/23 - today

4) Zone 5 6th Floor - 12/08/23 - tommorow

5) Zone TB/1 5th Floor - 14/08/23

7) Pile cap F/12 - 14/08/23

Please take note. 🙏👆
  Site progress picture.
11/8/23.
3rd floor. Zone 5. Slab rebar and M&E in progress.
 Azman HKL: 6th floor. Zone 5a. Slab rebar & M&E in progress..
Azman HKL: 6th floor. 5b. Slab formwork and scaffolding support in progress.
Azman HKL: 5th floor. Zone 4. Column rebar and formwork in progress.
Azman HKL: 5th floor. TB1. Slab/beam rebar in progress.
Azman HKL: 3rd floor. Slab formwork in progress
 Azman HKL: Basement. 8d. Slab cast.
 Azman HKL: Basement earthwork in progress.
Azman HKL: Basement. Slab foundation work in progress.
Azman HKL: 1st floor. TB2. Slab beam rebar in progress.
 Azman HKL: Ground floor. TB3. Slab formwork in progress. Basement, 8a. Staircase rebar in progress.
 Azman HKL: Ground floor. Genset silencer in progress.
 Raymond Chong. Y. F (HKL P. Manager): why don't erect brick wall 1st then only install?
 Azman HKL: 😱 @~LO KEAM @~. tolong pencerahan.. nanti saya cakap tidak ngam bah.. 🙏🙏🙏
 +60 19-895 9900: Pls liase wit my installer on site, they should know the sequence, if bricks wall laying facing problem by this way pls let us know, we coordinate on site, tqtq
 Raymond Chong. Y. F (HKL P. Manager): usually they let bricklayers know the bottom level, after that they install the silencer or we provide sufficient opening for them
 Raymond Chong. Y. F (HKL P. Manager): don't forget we need to provide lintol beam at the top of the silencers
+60 19-895 9900: Ok bos, already we coorsinate wit bricks layer,no problem, tq
Azman HKL: Basement. Ejector room. Ready for floor screeding.
 Azman HKL: Basement water tank room. Floor screeding in progress.
Azman HKL: 3rd floor. Zone 6. M&E inspection 2pm. Site PIC please make sure it is ready and report early if there is any obstruction on site. 🙏🙏
 Azman HKL: 1st floor. TB2. Beam rebar in progress..
 Azman HKL: 3rd floor. Zone 6. Slab. M&E inspection in progress..
 +60 17-866 0355: 3rd floor zone 6
M&E inspection done
 Azman HKL: @~Nasri 3rd floor, zone 6, M&E inspection siap ya. Boleh proceed..👌






































 