NSC GROUP
Azman HKL: Morning. @Leung KHπ @Edwin Chen 013 please check. We found that some water coming from outside thru this pipe sleeve at water tank room. If so, please put some stopper or end cap from outside pipe. ππurgent so we can start slab water proofing.
+60 17-866 0355: Azman boleh tolong pindah ni besi tidak dapat pasangan conduit
sangkut
Azman HKL: Saya try atur la ya. Kalau saya saturang tidak siap tu sampai petang. Sda inform sama subcon. Nanti mereka atur juga tu. πππ
Edwin Chen 013: The water is coming out from the pipe.
Raymond Chong. Y. F (HKL P. Manager): luckily from the pipe not pipe sleeve
Azman HKL: π± macam mana kau naik tu tinggi. Dari dalam pipe kan. Maw tutup itu yang diluar.
Raymond Chong. Y. F (HKL P. Manager): end cap luar lo
Edwin Chen 013: Surelah. Overflow
Edwin Chen 013: The slope/gradient in this area is very minimal
Azman HKL: Site progress picture.
5/8/23.
5th floor. Zone 4. Slab rebar, formwork & M&E in progress.
Azman HKL: TA1.2nd floor. Lift wall rebar in progress. 3rd floor, slab scaffolding in progress.
Azman HKL: 5a. 6th floor. Slab formwork & lift wall in progress.
Azman HKL: 5b. 5th floor. Scaffolding in progress.column cast.
Azman HKL: TB2. 1st floor slab formwork in progress. 8A/7B, Basement staircase formwork in progress.
Azman HKL: 3rd floor. Zone 6. Slab formwork & lift wall in progress.
Azman HKL: Basement, earthwork & slab foundation in progress..
Azman HKL: Basement, earthwork in progress