NSC GROUP
EG MALL Azman: Good morning.
Site progress photo.
1/9/23.
6th floor. TB1. Slab cast.
EG MALL Azman: 2nd floor. TB2. Slab cast.
EG MALL Azman: 7th floor. Z4. Slab scaffolding and formwork in rebar. 6th floor. Column rebar in progress
EG MALL Azman: 6th floor. Z5. Lift formwork.
EG MALL Azman: 4th floor. TA1. Slab formwork, lift rebar in progress.
EG MALL Azman: Ground floor. TA3, column rebar in progress
EG MALL Azman: Ground floor. TB3/TB4. Slab formwork in progress. Basement, Z4. Slab foundation in progress.
EG MALL Azman: Ground floor, TB4. Slav formwork in progress
EG MALL Azman: Ground floor. Z2A. Column rebar and 3rd floor slab formwork & scaffolding in progress
EG MALL Azman: @Leung KH🍀 as we discuss earlier, we will excavate this area. Please arrange to transfer this water tank panel ASAP. 🙏