Thursday, August 31, 2023

01 SEP 23 HKL

NSC GROUP
 EG MALL Azman: Good morning.
Site progress photo.
1/9/23.
6th floor. TB1. Slab cast.
EG MALL Azman: 2nd floor. TB2. Slab cast.
 EG MALL Azman: 7th floor. Z4. Slab scaffolding and formwork in rebar. 6th floor. Column rebar in progress
EG MALL Azman: 6th floor. Z5. Lift formwork.
 EG MALL Azman: 4th floor. TA1. Slab formwork, lift rebar in progress.
EG MALL Azman: Ground floor. TA3, column rebar in progress
EG MALL Azman: Ground floor. TB3/TB4. Slab formwork in progress. Basement, Z4. Slab foundation in progress.
 EG MALL Azman: Ground floor, TB4. Slav formwork in progress
EG MALL Azman: Ground floor. Z2A. Column rebar and 3rd floor slab formwork &  scaffolding in progress
EG MALL Azman: @Leung KH🍀 as we discuss earlier, we will excavate this area. Please arrange to transfer this water tank panel ASAP. 🙏



















 

Tuesday, August 29, 2023

30 AUG 23 HKL

SITE GROUP
EG MALL Azman: 6th floor. TB1. @Kadapi J. PROMES request for inspection slab M&E services at 2pm.


EG MALL Azman: M&E inspection done.

NSC GROUP

EG MALL Azman: Good morning. Site progress photo.
30/08/23.
2nd floor. TB2. Slab cast.
EG MALL Azman: 4th floor. Z6. Slab formwork & beam rebar in progress.
EG MALL Azman: Ground floor. Z TB3. Slab formwork in progress.
EG MALL Azman: Basement. Z 8C, column rebar in progress.
EG MALL Azman: Basement. Z 8D. Column rebar in progress
EG MALL Azman: Morning. @Leung KH🍀 please don't forget to cover pipe sleeve outlet so water did not come in thru the pipe. Or else later difficult to close.🙏🙏
EG MALL Azman: 6th floor. TB1. Slab rebar and M&E in progress.
 EG MALL Azman: 6th floor. Z4. Column rebar and slab scaffolding/formwork inprogress
EG MALL Azman: 6th floor. Z5. Lift formwork & column rebar
 Raymond Chong. Y. F (HKL P. Manager): Dear DCC, Econmech and King Hong, kindly get all the plinths confirmed for this area as we are now proceeding to 7th floor here
Lo. W. H (HKL-Site Engineer): Dear all valued NSC, revised 7th floor from ABLT
 Raymond Chong. Y. F (HKL P. Manager): Dear all, site meeting starts now
 EG MALL Azman: 6th floor. TB1. M&E services at slab inspection done. @Mr. Voo @Lo. W. H (HKL-Site Engineer) please proceed.. 👌
Mr. Voo: 👍🏻
 Lo. W. H (HKL-Site Engineer): Thanks

























 

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...