Sunday, July 30, 2023

31 JULY 23 HKL

SITE GROUP
 Azman HKL: Good morning. 
@⁨Kadapi J. EG Mall Promess Gadapi⁩ 
Request for M&E on slab inspection, 2nd floor. TA1. At 10.30am.
 Azman HKL: 2nd floor. TA1. M&E inspection done. Please proceed.
Azman HKL: @⁨Kadapi J. EG Mall Promess Gadapi⁩ request inspection. 5th floor. Zone 5b. Tonite after rebar work is done. Please stay on site until work ready for inspection. 🙏🙏🙏





NSC GROUP
 Azman HKL: Dear all, JKKP will be visiting our site this week, please ensure all workers are working with FULL PPE, wearing Safety Harness when working at height/Edge of building all the time. ❗Thank you
Azman HKL: Good morning. 
Site progress picture.
31/07/2023.
2nd floor. TA1. Slab rebar & M&E in progress.
Azman HKL: 5th floor. Zone 4. Slab formwork in progress.
 Azman HKL: 5th floor. 5a/5b. Slab rebar & M&E in progress. 6th floor beam supports scaffolding in progress
Azman HKL: 2nd floor. Zone 6. Column formwork and lift formwork in progress
Azman HKL: 5th floor. TB1. Slab formwork in progress.
Azman HKL: Basement, 8c foundation slab in progress.
Azman HKL: Basement. 8a/8b . Staircase formwork in progress.
Azman HKL: TA 1. Slab rebar and pipe sleeve in progress
Azman HKL: 2nd floor, TA1. M&E inspection in progress..
Azman HKL: M&E inspection, comment some rectification work have to do (FF). Will continue inspection after rectification is done after lunch.
 Azman HKL: 2nd floor. TA1. M&E inspection in progress.
Azman HKL: 2nd floor, TA1. M&E done rectification. Inspection pass. @~Nasri @Mr. Voo can proceed.
 Mr. Voo: 👍🏻
 Mr. Voo: Push tu 5F zone 5b
 Azman HKL: 5th floor. M&E partial inspection in progress.

Azman HKL: Kabur bah..😅
+60 17-866 0355: Inspection
+60 17-866 0355: 5th floor M&E inspection
 done





























 

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...