Friday, July 28, 2023

29 JULY 23 HKL

NSC GROUP

Azman HKL: Site progress picture.
29/07/23
2nd floor. TA1. Slab rebar and M&E in progress.
 Azman HKL: 5th floor. Zone 4. Slab formwork, column, scaffolding in progress.
Azman HKL: 5th floor. 5a&5b. Lift wall in progress. Slab/Beam rebar in progress.
Azman HKL: 5th floor. TB1. Slab formwork in progress.
Azman HKL: 2nd floor. Zone 6. Column, parapet, lift wall in progress.
Azman HKL: Basement earthwork in progress.
Azman HKL: Basement earthwork in progress.
Azman HKL: Basement. 8a. Column rebar in progress.
Raymond Chong. Y. F (HKL P. Manager): Dear all, JKKP will be visiting our site next week, please ensure all workers are working with FULL PPE, wearing Safety Harness when working at height/Edge of building all the time. Thank you
Raymond Chong. Y. F (HKL P. Manager): @Edwin Chen 013 please arrange to shift all your materials/equipment here ASAP before occupied by others
Raymond Chong. Y. F (HKL P. Manager): the basement area for your storage is cleared
 Edwin Chen 013: Which area is this? So dark.
 Raymond Chong. Y. F (HKL P. Manager): here
Edwin Chen 013: Ok.
Azman HKL: Basement. TA2. Pipe sleeve thru beam inprogress.
+60 12-843 3877: Esoklah sambung.besi tak siap lagi💪
Azman HKL: Target cast on monday. 
1. 5th floor, 5b
2. 2nd floor. TA1.
3. Basement, 8c
4. GF, TA2.
Raymond Chong. Y. F (HKL P. Manager): Item 4 postpone to Tuesday
Azman HKL: Noted..👆






















 

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...