Azman HKL: Site progress picture
26/07/23.
5th floor. Zone 5a&5b. Slab rebar,formwork& M&E in progress.
Azman HKL: 5th floor. Zone 4. Slab formwork in progress.
Azman HKL: 2nd floor. TA1. Slab/beam rebar in progress.
Azman HKL: 4th floor. TB1. Column and slab scaffolding in progress.
Azman HKL: 2nd floor. Zone 6. Lift wall formwork, parapet wall and column in progress
Azman HKL: Basement. Zone 8b. Retaining wall formwork in progress.
Azman HKL: Inspection lift opening with Mitsubishi. Comment: door opening need to adjust 10mm(L)and 30mm(R) as marked by Mitsubishi. TQ👌
Azman HKL: @Kadapi J. PROMES Request for M&E services inspection. 2.00pm. Slab.5th floor. Zone 5a.
NSC GROUP
Raymond Chong. Y. F (HKL P. Manager): @Azman HKL @Edwin Chen 013
Azman HKL: 2nd floor. Zone TA1. Slab bottom rebar in progress.
Azman HKL: M&E inspection in progress at 5th floor slab zone 5a.
Azman HKL: Basement. Slab rebar in progress.
Azman HKL: 5th floor slab. Zone 5a. Done M&E inspection with consultant. @Mr. Voo @~Nasri please proceed.