SITE GROUP
Azman HKL: Good morning. Site progress picture.
25/07/23
1. 2nd floor. Zone TA1. Slab formwork and beam rebar in progress.
Azman HKL: 2. 5th floor. Zone 4. Slab formwork in progress.
Azman HKL: 3. 5th floor. Zone 5a. Slab/beam rebar & M&E in progress.
Azman HKL: 5th floor. Zone 5b. Slab formwork in progress.
Azman HKL: 2nd floor. Zone 6. Parapet wall, column & lift wall rebar in progress.
Azman HKL: 4th floor. TB1. Column in progress.
Azman HKL: Basement. 8a. Column Rebar & formwork in progress
Azman HKL: Basement. 2C. Earthwork slab foundation in progress.
Azman HKL: @~YoonYK tomorrow morning request to check lift wall dimension and opening. ππ
Azman HKL: BL1, supermarket, 2nd floor.
+60 19-821 8251: Ok, tomorrow 9am then.π
Azman HKL: Ok. Bsok jam 9.00am. @Kadapi J. PROMES satu kali kita inspection. π
Kadapi J. PROMES: Ok bah klu ko