Azman HKL: Site progress picture.
24/07/2023.
1. 5th floor. Zone 4. Slab scaffolding in progress.
Azman HKL: 2. 5th floor. Zone 5a. Slab formwork, rebar & M&E services in progress.
Azman HKL: 3. 5th floor. 5b. Slab formwork in progress.
Azman HKL: 4. 2nd floor. Zone 6. Column, parapet & lift wall rebar in progress.
Azman HKL: 5. Basement zone 7a. Column rebar in progress.
Azman HKL: 6. 2nd floor. Slab formwork in progress.
Lo. W. H (HKL-Site Engineer): Dear valued NSC, here are revised floor plan issued out by ABLT
Lo. W. H (HKL-Site Engineer): please study your scope services in related this revised floor plan
Lo. W. H (HKL-Site Engineer): Still have changes for M&E rooms
Lo. W. H (HKL-Site Engineer): Will relocate chiller room
Lo. W. H (HKL-Site Engineer): Smoke spill fan room as well
Azman HKL: Ground floor. Zone 2. Slab formwork in progress.
Raymond Chong. Y. F (HKL P. Manager): TA/2a