NSC GROUP
Azman HKL: Good morning.
Site progress picture.
21/07/2023.
Zone 4. 4floor. Slab cast.
Azman HKL: Zone 5a. 5th floor. Slab formwork and beam rebar in progress.
Azman HKL: Zone 4. 4th floor. Column rebar in progress
Azman HKL: Basement. 8a. Column rebar in progress.
Azman HKL: Zone 6. 2nd floor. Column rebar, M&E conduit & lift wall formwork in progress
Azman HKL: 2nd floor. TA1. Slab formwork and lift wall formwork in progress.