SITE GROUP
Azman HKL: Good morning.
Site progress picture.
20/07/23
4th floor. Zone 4. Slab rebar & M&E in progress.
Azman HKL: Zone 5. 5th floor. Slab formwork in progress.
Azman HKL: Zone4. 4th floor. Column rebar and formwork in progress.
Azman HKL: Zone 6. 2nd floor. Column rebar and lift wall formwork in progress.
Azman HKL: 2nd floor. Zon TA1. Slab formwork & 1st floor lift rebar in progress.
Azman HKL: Basement. Retaining wall.
NSC GROUP
Azman HKL: Basement. 2a. Column and ground floor scaffolding in progress.
Azman HKL: @~ShawnChia please confirm me. Your Genset subcon informs me that early August, they will start hanging that inlet/outlet silencer so that the brick wall below can start.
Raymond Chong. Y. F (HKL P. Manager): Azman, early August is too late, we need to complete the brick wall soonest
Raymond Chong. Y. F (HKL P. Manager): can ask them to do it next Monday?
+60 19-895 9900: @Azman HKL pagi bos, hav u checked the genset room wall to be double bricks all 4 wall as per our discussion the other day site inspection?
Raymond Chong. Y. F (HKL P. Manager): yes, but we can't proceed the brick walls at the moment as your equipment need to reposition
Raymond Chong. Y. F (HKL P. Manager): DCC, when is the delivery date for the Genset room and Exhaust lourves?
+60 19-895 9900: Hi Mr Raymond, this single brick wall hav to demolish?
Raymond Chong. Y. F (HKL P. Manager): where is this wall?
+60 19-895 9900: Genset room grd floor sir
+60 19-895 9900: ππ»
Raymond Chong. Y. F (HKL P. Manager): this is the genset door side right?:
Lo. W. H (HKL-Site Engineer): which side?
+60 19-895 9900: Staitcase side
Lo. W. H (HKL-Site Engineer): it is single brick as drawn on layout and staircase lobby
+60 19-895 9900: Other side double wall
+60 19-895 9900: We advise to hav all double wall in order to achieve DOE acoustic requirement more efficient
+60 19-895 9900: If consultant said ok let it be to us no issue as long as we hav advise ππ»ππ»ππ»
+60 19-895 9900: Eventually we hav to get dB report during T&C
+60 19-895 9900: Hope that clarified, tq allππ»ππ»ππ»
Lo. W. H (HKL-Site Engineer): noted
Azman HKL: πlater can discuss with consultant in meeting.
Azman HKL: Please help me to inform your subcon if they can come in next monday. πππ
Lo. W. H (HKL-Site Engineer): ok it should be double
+60 19-895 9900: We know the urgency and i hav talk to my installer on our schedule, early Aug was the last schedule but we try our best to make it earlierππ»ππ»ππ»
Azman HKL: Ok. Thanks. πͺ
Azman HKL: @~Leppong ready sda untuk inspection kamu punya item di zone 4, 4th floor?
+60 17-866 0355: ya ready sudah man
Azman HKL: Ok.. otw. Jam 2pm.
+60 17-866 0355: Ok man
Azman HKL: @~Walker Yapi kamu punya?
+60 14-379 2990: Ready sudah..
Azman HKL: M&E services inspection in progress..
Azman HKL: Done M&E inspection and repair works. Can proceed. π