19 JULY 23 HKL

NSC GROUP

 Azman HKL: Good morning. 
Happy New year.. 
Site progress picture. 
19/07/2023.
TA1. 2nd floor. Slab formwork in progress. 1st floor lift wall cast.
 Azman HKL: Zone 4. 4th floor. Slab rebar in progress. M&E in progress.
Azman HKL: TB1. 4th floor. Column rebar & formwork in progress.
 Azman HKL: 5a. 5th floor. Slab formwork in progress.
Azman HKL: 5b. 5th floor. Slab formwork in progress.
Azman HKL: Zone 6. 2nd floor. Column rebar in progress.
 Azman HKL: Basement. Zone 8C. Earthwork
Azman HKL: Basement, 8a. Dismantling retaining wall rebar in progress.
Azman HKL: Basement, 2C. Retaining wall rebar and column rebar in progress..
Azman HKL: Tinggal ini tempat lagi belum pasang?
+60 17-866 0355: ya man



















 