NSC GROUP
+60 17-866 0355: Azman boleh tolong pindah ni besi tidak dapat pasangan conduit
Azman HKL: Ok bro..
+60 17-866 0355: 4th floor
+60 17-866 0355: TQ broo
Azman HKL: Site progress picture.
18/07/2023.
2nd floor. Zone 6. Slab cast.
Azman HKL: Basement, zone 8b. Slab cast.
Azman HKL: Basement. Zone 8a. Retaining wall cast.
Azman HKL: View mata helang..
Azman HKL: 5th floor. 5a. Slab formwork in progress.
Azman HKL: 4th floor. Zone 4. Slab rebar and M&E in progress.
Lo. W. H (HKL-Site Engineer): Dear all valued NSC, the above is the latest revised archi drawing that we have as of today
Lo. W. H (HKL-Site Engineer): kindly take note, if the layout affected your M & E services
Dart Econmech: Do u hv cad file?
+60 19-895 9900: Can email to our ofis?
Edwin Chen 013: Better by email. Make it official
Lo. W. H (HKL-Site Engineer): I have requested but not being entertained yet....once receive will share or email you all
Dart Econmech: Sure affected la
+60 19-895 9900: PDF also pls email to ofis pls๐๐ป๐๐ป๐๐ป
Lo. W. H (HKL-Site Engineer): Noted
+60 19-895 9900: Tqvm
Lo. W. H (HKL-Site Engineer): Please be reminded that all this drawing is subjected to another round of amendments, if any