SITE GROUP
Azman HKL: Site progress picture.
17/07/2023.
2nd floor. Zone 6. Slab top rebar & M&E in progress.
Azman HKL: 4th floor. Zone 4. Slab rebar and M&E in progress.
Azman HKL: Zone 5a. 5th floor. Slab formwork in progress
Azman HKL: Zone 5b. 4th floor. Parapet wall formwork & slab scaffolding for 5th floor in progress.
Azman HKL: 2nd floor. Zone TA1. Slab formwork in progress. 1st floor. 1ft wall rebar in progress.
Azman HKL: Basement. 8a. Retaining wall form work in progress.
Azman HKL: Basement. 8b. Slab rebar in progress
NSC GROUP
+60 17-866 0355: Level 2, zone 6.
Azman HKL: Site progress picture.
17/07/2023.
2nd floor. Zone 6. Slab top rebar & M&E in progress.
Azman HKL: 4th floor. Zone 4. Slab rebar and M&E in progress.
Azman HKL: Zone 5a. 5th floor. Slab formwork in progress
Azman HKL: Zone 5b. 4th floor. Parapet wall formwork & slab scaffolding for 5th floor in progress.
Azman HKL: 2nd floor. Zone TA1. Slab formwork in progress. 1st floor. 1ft wall rebar in progress.
Azman HKL: Basement. 8a. Retaining wall form work in progress.
Azman HKL: Basement. 8b. Slab rebar in progress
Edwin Chen 013: @Lo. W. H (HKL-Site Engineer) @Azman HKL , is the new Ejector Room location is confirmed?
Lo. W. H (HKL-Site Engineer): Ya
Azman HKL: Please take note ya. 2nd floor, slab zone 2. Casting plan by today. RFI at 2pm.
Azman HKL: 2nd floor, zone 6. Ramp 4. Top rebar & M&E in progress.
Azman HKL: M&E inspection in progress..
Azman HKL: Done M&E inspection can proceed. @Mr. Voo @~Nasri