Azman HKL: Good morning.
Site progress picture.
13/7/23.
5a. 5th floor. Slab formwork and scaffolding. 4th floor. Lift wall rebar in progress. Column rebar in progress.
Azman HKL: 4th floor. Zone 4. Slab formwork in progress.
Azman HKL: 2nd floor. Slab formwork in progress. 1dt floor, Lift wall rebar in progress.
Azman HKL: 4th floor. TB1.
Azman HKL: @
Azman HKL: @Leung KHπ @Edwin Chen 013 @~Walker Yapi @Dart Econmech tolong atur pindah ni barang. TC ada sana juga bileh tolong.
Dart Econmech: Ok man
Leung KHπ: Ok boss ππ»
Azman HKL: Itu pipe lagi.
+60 14-379 2990: @Azman HKL, kami mahu request Tower Crane 1 jam (1pm - 2pm) unload pipe kami pergi Groundfloor..
+60 14-379 2990: 12 bundle only.
+60 14-379 2990: 4pm forklift mesti keluar dari genset room area. ππ»ππ»ππ»
+60 19-895 9900: @Azman HKL AS Per our join inspection this mrng together wit the Genset supplier & forwarder PIC, this entrance to be clear & fit for 26+10tonnes (biggest load) lori crane to access & unload, kindly assist to clear and enhance the surface access road , tqvmππ»ππ»ππ»
+60 19-895 9900: We wil try our utmost efford to complete the unloading before evening provided the weather is fit to do so
Azman HKL: Awal pagi bah request sama itu signalman tidak sibuk. Atur awal2 jam 8-9 pagi. Jam 1 tu maw casting level 4. Concrete sda order.
+60 19-895 9900: ππ»ππ»ππ»
Azman HKL: Ok, noted. Clearing is in progress. This afternoon hitachi will coming to repair the access road and hope the weather will help us. π
Azman HKL: Today morning inspection & checked by myself, main entrance roadway still NOT YET READY & prepare for us...
Azman HKL: All wooden foamworks, pallets of red bricks, mobile dustbin blocked the roadway...
Azman HKL: The road still NOT YET improve, touch up... Need to compact & level it by before this Saturday...
Azman HKL: With main~con site co~ordinator incharge, Mr. Azman...
Azman HKL: All the steels materials NEED TO BE CLEAR for our lorry crance parking & cranage position works...
Azman HKL: All the materials at this portion area NEED TO BE CLEAR...
Azman HKL: NOTE: THE ROADWAY still NEED TO COMPACT & LEVEL by using excavator...
Azman HKL: # CC forwarded to Mr. Alex, Mr. Sean, DCC Management, Main~Con, Mr. Azman...
Azman HKL: Hope main~con, ur side can on time prepare & ready the site for us, bro... π¬ππ»ππ»ππ» Tq Tq...
Azman HKL: @Raymond Chong. Y. F (HKL P. Manager) @Mr. Voo @~Nasri comment from genset suplier..
Azman HKL: Remain this area, TS Wong has to clear by today so hitachi can level the area.
Azman HKL: I already arranged with @~Nasri so hitachi can come in to level this area by this afternoon.
+60 14-379 2990: Thanks yaa @Azman HKL ,@~Nasri ..ππ»ππ»ππ»