NSC GROUP
Edwin Chen 013: @Azman HKL , How is the progress on the water tank area in the basement? Do you need to do any paintwork on the plinth?
+60 16-526 1788: Painting come later, install je
Raymond Chong. Y. F (HKL P. Manager): No painting to plinth is required
Edwin Chen 013: Ok. We will initiate and mobilize our team soon to install the FRP tank. Thanks.
Azman HKL: Epoxy paint to plinth? Not in BQ and detail drawing. Please advise if there is a requirement. Can you help me to confirm with Promes if need that epoxy paint.
Raymond Chong. Y. F (HKL P. Manager): Hold on 1st, we need to screed the floor before u can install
Edwin Chen 013: I mean soon. Not now. Let me have an indicative date when we are allowed to start our work. Thanks
Raymond Chong. Y. F (HKL P. Manager): Ok
Azman HKL: Site progres picture.
11/7/23.
4th floor. 5b. Cast.
Azman HKL: 5th floor. 5a. Slab beam formwork in progress.
Azman HKL: 4th floor. Slab rebar & M&E in progress.
Azman HKL: 2nd floor. Zone 6. Slab formwork in progress
Azman HKL: 4th floor. Zone 4. Slab formwork in progress
Azman HKL: 2nd floor. Slab formwork in progress. 1st floor. Lift formwork & rebar in progress
Azman HKL: Basement. 8a. Retaining wall rebar inprogress
Edwin Chen 013: Not their scope.
Azman HKL: Ok thanks.👌
Azman HKL: Coordination meeting. 3pm after subcon meeting.
Azman HKL: Simpan tak di ramp
No comments:
Post a Comment