Friday, July 7, 2023

08 JULY 23 HKL

   SITE GROUP

 Kadapi J. PROMES: Aku off dulu. Aku kurang sihat.

Azman HKL: Ok noted bossku. πŸ‘Œ

NSC GROUP

+60 16-832 0082: Tqvvm πŸ™πŸ™
 Azman HKL: Morning. @~Lawrence Yapp @~LO KEAM please advise & confirm. Genset plinth need epoxy paint? Not show in detail. πŸ™πŸ™.
+60 19-895 9900: Pagi bos, pls check the building contract, we hav no specific requirement on this, its under builder's work, hope this clarified, tqπŸ™πŸ»πŸ™πŸ»πŸ™πŸ»
 +60 19-895 9900: By the way we scheduled to sit the Genset in next Sat, r the plinth ready for that?pls advise tq
Raymond Chong. Y. F (HKL P. Manager): should be OK
Lo. W. H (HKL-Site Engineer): in our building contract also not show
 +60 19-895 9900: Then should be not required πŸ˜„
 +60 19-895 9900: Just smooth screed will do, tq
 Lo. W. H (HKL-Site Engineer): Please ask Ir. Lan, if any
 Lo. W. H (HKL-Site Engineer): all M & E room ...building contract did not show any thing about Epoxy paint
 Azman HKL: Site progress picture. 
8/7/2023.
4th slab, zone 5b, formwork, slab rebar and M&E conduit in progress.
Azman HKL: 4th floor. TB1. Slab formwork and beam rebar in progress.
.
Azman HKL: Basement, zone 2B, retaining wall formwork in progress.
Azman HKL: 2nd floor, zone 6. Slab formwork in progress.
Azman HKL: Basement. Zone 8a. Retaining wall rebar in progress.
 Azman HKL: Basement zone 2c. Slab formwork in progress.
Azman HKL: Casting Plan
1. 4th floor. Zone 5b -11/07/23
2. Basement, 3A1. RC wall - today 8/7/23.
3. 2nd floor. Zone 6. 18/7/23
4. 4th floor. TB1. 13/7/23