Mr. Voo: @Azman HKL lama lagi kah ?
Mr. Voo: Concrete sya sampai sdh
Azman HKL: Site progress picture.
4/6/2023.
4th floor. Zone 5a. Slab will be cast by today.
Azman HKL: 4th floor. Zone 4. Slab formwork in progress.
Azman HKL: 4th floor. Zone TA1. Slab formwork in progress.
Azman HKL: 1st floor. Lift wall formwork and, 2nd floor slab formwork support in progress.
Azman HKL: 2nd floor, zone 6. Slab formwork in progress.
Mr. Voo: Suruh org kasih bersih tu jalan ya
Azman HKL: Basement. Retaining wall rebar.
Azman HKL: Basement, ejector room. Cast plan by today.
Azman HKL: Basement, Chiller room. Setting out in progress.
Azman HKL: Ground floor. Genset room area.
Azman HKL: MSB room area.
Azman HKL: Transformer room area.
Azman HKL: Basement water tank room area.
Azman HKL: Basement, fire watertank room area.
Azman HKL: @Dart Econmech @~Walker Yapi ini jalan hari ini itu pump konkrit masuk sini cast lantai 4th floor. 5a.
Dart Econmech: Ganti2 la kan. lpas unload pipe gitu
+60 16-832 0082: Genset will deliver to site by this week, minta clear tempat ni ya..saya belanja ais potong 🤣🤣🤣
Azman HKL: Today M&E meeting 3pm. Site meeting room.
Azman HKL: Ni malam mereka kasi clear, bsok start kasi setting up itu plinth..