Monday, July 31, 2023

01 AUG 23 HKL

 

NSC GROUP

Azman HKL: Good morning.
Site progress picture.
1/8/23.
2nd floor. TA1. Slab cast.
Azman HKL: 5th floor. Zone 5b. Slab cast.
 Azman HKL: 5th floor. Zone 4. Slab formwork in progress.
 Azman HKL: 6th floor. Zone 5a. Slab formwork in progress. 5th floor. Lift wall formwork in progress.
Azman HKL: 2nd floor. Column formwork, lift formwork, 3rd floor slab formwork in progress.
Azman HKL: Basement. 8c/8d. Slab foundation cast.
 Azman HKL: Ground floor. TA2. Slab/beam rebar in progress. NSC please check ur item. Thanks. 🙏