Azman HKL: Good morning.
Site progress picture.
39/06/2023.
4th floor, zone 5a. Slab bottom rebar & M&E in progress.
Azman HKL: 4th floor. Zone 4. Slab formwork in progress.
Azman HKL: 4th floor. Zone 5b. Slab formwork & bottom rebar in progress.
Azman HKL: 4th floor. Zone TB1. Slab formwork in progress.
Azman HKL: 1st floor. Zone 6. Lift wall formwork, column formwork in progress.
Azman HKL: Basement zone 8a cast.
Azman HKL: Basement zone 8b, slab foundation rebar in progress.
Azman HKL: Basement, Zone 3c
Azman HKL: 1st floor. TA1. Lift wall formwork, support scaffolding in progress.
NSC GROUP
Azman HKL: 4th floor, 5a. Target cast by today. Site PIC please double check your services. Inform early any problem. All plinths and openings please confirm and inform. Work in teamwork. Your cooperation is very appreciated.. πͺπͺπ
Azman HKL: DCC on site install conduit on slab. πͺππΏππΏπ
Azman HKL: Daily report, report like this format. Uniform to all. π
Dart Econmech: @Azman HKL latest info. Container arrived on site on monday nextweek
Azman HKL: Okay. What time arrived? Need to clear parking area.
Dart Econmech: Morning. 9am - 10am
Azman HKL: Ok.
Azman HKL: Conduit for M&E services in progress.πͺ