Thursday, June 22, 2023

23 JUNE 23 HKL

NSC GROUP

 Azman HKL: Good morning 🌄
Site progress picture.
23/06/2023.
4tg floor. Zone 5a/5b. Slab formwork in progress.
 Azman HKL: 4th floor. Zone 4. Slab scaffolding & formwork in progress.
Azman HKL: 1st floor, zone 6. Column rebar and formwork in progress
Azman HKL: 1st floor. Lift formwork & column rebar in progress
 Azman HKL: 4th floor. Zone TB1. Slab formwork in progress.
Azman HKL: Basement, zone 8a. Slab foundation rebar in progress.
Azman HKL: Basement zone 3a. Retaining wall in progress.
Azman HKL: Basement, brickwall cutting for conduit in progress.
Azman HKL: Basement, undercoat ceiling for electrical trunking.
Azman HKL: Basement retaining wall. Rebar in progress. Target 1st cast, monday 26/06/23.



















 