SITE GROUP
Azman HKL: Site PIC, tolong ya. Check kali2 itu drawing. Opening, plinth, tolong ready awal. Jangan tunggu masa inspection baru maw cari itu detail semua. Saya punya drawing tidak lengkap so tolong kejar kamu punya opis.. πππ.
Edwin Chen 013: @Azman HKL , any arrangement to cast the plinth for the Ejector pump ?
Azman HKL: By this week. the slab plinth for pump & chiller.
Azman HKL: Stanby for inspection with consultant.
NSC GROUP
Azman HKL: Morning.
Site progress picture.
21/06/2023.
3rd floor. TB1. Slab floor cast.
Azman HKL: 1st floor. Zone 6. Slab rebar and M&E in progress.
Azman HKL: 1st floor. TA1. Slab rebar & M&E i. Progress.
Azman HKL: 4th floor. Slab formwork in progress.
Azman HKL: 3rd floor. Zone 4. Dismantling water tank plinth formwork in progress.
Azman HKL: Basement. Zone 8a. Slab rebar in progress.
60 17-866 0355: Azman boleh tolong pindah ka ni besi kami mau jalan conduit
Azman HKL: Ok. Kalau ada apa masalah kasi inform saya. ππͺπͺ
Azman HKL: @Dart Econmech tidak sempat ni kalau 1 org. Hari ini ada 2 lantai tolong atur. Urgent!!ππΏππΏππΏ
Dart Econmech: Ok man
Azman HKL: 1st floor, zone 6. Conduit in progress..
Mr. Voo: Done ?
Azman HKL: M&E inspection in progress. 1st floor. Zone 6.
+60 12-843 3877: Besi belum siap@Azman bro.tak boleh jalan conduitππ»
Azman HKL: 1st floor. Zone 6. Inspection done. Can proceed. @Mr. Voo @~Nasri
Mr. Voo: ππ»
Azman HKL: 1st floor. Zone TA1. M&E works in progress.
Azman HKL: M&E pre-inspection in progress.
Mr. Voo: Jam 6 pump semen paking..
Mr. Voo: Leong
Leung KHπ: Okayππ»
Mr. Voo: ππ»
Mr. Voo: Tq
Mr. Voo: Zone TA/1 m&e done ?
Azman HKL: Sorry.. zone TA1, M&E done.π
Azman HKL: Inspection done
Mr. Voo: ππ»