Monday, June 19, 2023

20 JUNE 23 HKL

SITE GROUP
 Dart Econmech: @Azman HKL
Dart Econmech: Pipes delivery eta
Dart Econmech: Delay2 bln 7 la
Dart Econmech: Awl bln 7
Azman HKL: For info ok. Kasi formal dia by letter to HKL.. detail, saiz, berat, protection. Nanti setup mana maw storage. πŸ™
Dart Econmech: Ok man
Azman HKL: 3rd floor. Zone TB1. NSC please double check your services. If no services please inform. Make Sure housekeeping after installation. Submit RFI to get inspected
 Azman HKL: @Kadapi J. PROMES request M&E inspection 10am. 3rd floor slab, TB1.
Kadapi J. PROMES: Pump sump blum buat lagi ni.
Raymond Chong. Y. F (HKL P. Manager): Grease trap height is 1.06m
Raymond Chong. Y. F (HKL P. Manager): Baru dapat pagi tadi dan tunggu detail dr Lan

NSC GROUP

Azman HKL: Conduit potong tidak pakai kasi keluar.. 3rd floor. TB1.. πŸ‘†@~Leppong
Raymond Chong. Y. F (HKL P. Manager): Grease trap height is 1.06m
Raymond Chong. Y. F (HKL P. Manager): @Azman HKL tolong check dengan Kadapi
 Azman HKL: Ok bos. Ini pagi sy check sama dia.
Azman HKL: 3rd floor. TB1. Slab rebar & M&E in progress.
 Azman HKL: 1st floor. Zone6. Slab rebar & M&E in progress.
Azman HKL: 1st floor. Zone TA1. Slab rebar in progress.
Azman HKL: Basement 8a&8b. Slab foundation rebar in progress.
Azman HKL: 3rd floor. Zone 4. Watertank plinth in progress.
+60 17-866 0355: Ok man sudah

Azman HKL: 3rd floor slab. M&E pre-inspection. Next after rebar installation complete.
+60 12-843 3877: M&E inspection@3rd flr
 Azman HKL: 1st floor. TA1. Conduit on the slab in progress.
 Azman HKL: 1st floor. Zone 6. M&E services on slab in progress.
Azman HKL: M&E inspection done.πŸ‘Œ
 Azman HKL: @~Walker Yapi daily record. 🫰

Azman HKL: Setiap hari waktu bekerja ok. 

































 