NSC GROUP
Azman HKL: Giid morning.
Site progress picture.
19/06/2023.
3rd floor. TB1. Slab rebar & M&E services in progress.
Azman HKL: 4th floor. Zone 5. Slab formwork in progress.
Azman HKL: Basement. Zone 8. Slab foundation rebar in progress.
Azman HKL: Basement. Zone 8. Slab foundation rebar inprogress
Azman HKL: 1st floor. Zone 6. Slab formwork and rebar in progress.
Azman HKL: Basement. 3A. Fire watertank plinth cast..
Azman HKL: 1st floor. TA1. Slab and beam formwork/rebar in progress
Azman HKL: @Dart Econmech @~Walker Yapi please check your duct opening at slab. Slab in progress. Plan earlier. Please communicate with supervisor & subcon. 🙏🙏
Azman HKL: @Edwin Chen 013 @Leung KH🍀 basement slab in progress. Need your ejector plinth and pump sump confirmation.🙏🙏
Raymond Chong. Y. F (HKL P. Manager): this area slab casting on 21/06/23, please take note
Azman HKL: 3rd floor. TB1. Conduit runs at the slab.
Azman HKL: 3rd floor water tank plinth in progress.
Azman HKL: 1st floor. Zone 6. Slab rebar in progress.
Azman HKL: Update casting plan
21/06/2023.-
1. 1st floor, Zone 6.
2. 1st floor, zone TA1. GL: F-I/3-5.
24/06/2023.-
Basement, zone 8a, 8b.
(2 times cast)
Azman HKL: @~ShawnChia for this two area zone 6& TA1, please plan maybe you need 2 installer team on site.
Azman HKL: TA1.
+60 16-837 8881: 👌🏻