Friday, June 16, 2023

17 JUNE 23 HKL

SITE GROUP
Azman HKL: Good morning. 
Site progress picture.
16/06/2023. 3rd floor. Zone 4. Slab cast.
Azman HKL: 3rd floor. Zone TB1. Slab rebar in progress.
 Azman HKL: 4tg floor. Slab formwork in progress
Azman HKL: Basement zone 8. Slab foundation rebar in progress.
Azman HKL: 1st floor. Zone TA1. Beam rebar and slab formwork in progress. Lift rebar in progress.
 Azman HKL: 1st floor. Zone 6. Slab formwork and beam rebar in progress.

  NSC GROUP


Azman HKL: Hi. Morning @Leung KH🍀 @Edwin Chen 013 can we get the other ejector pumpset plinth detail so we can setup at site. That room layout is different.
Azman HKL: Ejector room..
Raymond Chong. Y. F (HKL P. Manager): Azman, there will be changes at this area, King Hong please consult Promes ASAP for advise
 Azman HKL: Ok bos noted.
Edwin Chen 013: No changes according to Promes.
Raymond Chong. Y. F (HKL P. Manager): then proceed
Azman HKL: @Edwin Chen 013 request that plinth detail layout.. 🙏
Azman HKL: DCC runs conduit at 3rd floor, zone TB1.
 Edwin Chen 013: Will send later

















 