Kadapi J. PROMES: Aku cuti ni hari aaa. Tapi on call kalau ada urgent inspection. Tq
NSC GROUP
Azman HKL: @Azman HKL bottom bar siap
+60 17-866 0355: Ok man
Azman HKL: 3rd floor. 5b.
Azman HKL: Site progress picture. 12/06/2023.
3rd floor zone 5. Slab rebar and lift wall rebar in progress.
Azman HKL: 3rd floor. Zone 4. Slab rebar in progress.
Azman HKL: 1st floor. TA1. Slab formwork in progress. Lift wall rebar in progress.
Azman HKL: 3rd floor. Zone TB1, slab formwork and in progress.
+60 12-843 3877: Belum boleh lagi jalan conduit๐
Azman HKL: Ground floor, zone 7. Lift wall formwork and column rebar in progress.
Azman HKL: Basement, TB 4 slab foundation rebar in progress.
Azman HKL: Basement, zone 3. Plinth for Fire water tank in progress.
+60 12-843 3877: Dcc marking point๐
Azman HKL: @~Walker Yapi @~DartWeirdo ๐ฒ๐พ please do double check that plinth. Submit RFI for approval by consultant. Kerjasama anda amat di dihargai dan alu-alukan. ๐
Azman HKL: Chiller room ready. Boleh setup plinth dgn subcon. Nanti boleh cast satu kali.
Azman HKL: @Leung KH๐ @Edwin Chen 013 boleh check level water tank plinth.
+60 17-866 0355: basement. Lightning
Azman HKL: Casting plan, 3rd floor. Zone5b, 13/06/2023. Tuesday. Please take note. ๐๐ช๐ช๐ช