10 JUNE 23 HKL

 NSC GROUP


Azman HKL: Good morning. 
Site picture progress. 
10/06/2023.
3rd floor. Zone 5a. Lift wall rebar in progress.
 Azman HKL: 3rd floor. Zone 4. Slab rebar in progress.
 Azman HKL: 3rd floor. Zone TB1. Slab formwork in progress.
 Azman HKL: 1st floor. Zone TA1. Slab formwork and lift rebar.
Azman HKL: Ground floor. Zone TB2. Column rebar in progress.
 Azman HKL: Basement TB3. Column rebar in progress.
 Azman HKL: Basement, TB4 slab foundation in progress.
Azman HKL: Ground floor. Zone 7. Column rebar in progress.

Azman HKL: Fire water tank plinth setting out in progress..
 +60 10-941 8970: Nanti suruh diorang tutup ni yeh maw timbun besok
 +60 10-941 8970: Thank you
 Azman HKL: @Leung KH🍀 tutup guna plastik supaya air hujan sama tanah tidak masuk dalam.


 Azman HKL: Bin center room lintol beam and wall tatai in progress.
 Azman HKL: Ground floor, Upvc pipe at high level in progress.