Site picture progress.
10/06/2023.
3rd floor. Zone 5a. Lift wall rebar in progress.
Azman HKL: 3rd floor. Zone 4. Slab rebar in progress.
Azman HKL: 3rd floor. Zone TB1. Slab formwork in progress.
Azman HKL: 1st floor. Zone TA1. Slab formwork and lift rebar.
Azman HKL: Ground floor. Zone TB2. Column rebar in progress.
Azman HKL: Basement TB3. Column rebar in progress.
Azman HKL: Basement, TB4 slab foundation in progress.
Azman HKL: Ground floor. Zone 7. Column rebar in progress.
Azman HKL: Fire water tank plinth setting out in progress..
+60 10-941 8970: Nanti suruh diorang tutup ni yeh maw timbun besok
+60 10-941 8970: Thank you
Azman HKL: @Leung KH🍀 tutup guna plastik supaya air hujan sama tanah tidak masuk dalam.
Azman HKL: Bin center room lintol beam and wall tatai in progress.
Azman HKL: Ground floor, Upvc pipe at high level in progress.