SITE GROUP
Azman HKL: Bossku. Request for inspection. @Kadapi J. PROMES .
1) 3rd floor. Zone 5a. Slab.
2) Basement, zone 3b. Slab.
3) lift opening at wall.
Today, 3.00pm.
Kadapi J. PROMES: 👌👍
Azman HKL: NSC, @~Walker Yapi @~. PIC please stanby for inspection. 3rd floor. Ready with RFI form and drawing. 3pm.
Azman HKL: M&E inspection inprogress.
Azman HKL: Ground floor, lift wall opening for Hotel & Office inspection with consultant & Mitsubishi.
NSC GROUP
+60 19-821 8251: Morning, kindly inform the inspection for lift shaft at area TA1 yet ready for inspection. @Azman HKL
+60 19-821 8251: Afternoon will come back again, thanks.
Azman HKL: Noted. Will arrange..
Azman HKL: Morning. Mitsubishi on site to mark and inspect lift opening at the wall. Will come again in the afternoon to check boxes.
Azman HKL: Site progress picture.
8/06/2023.
3rd floor. Zone 5a. Slab rebar & M&E services in progress.
Azman HKL: 3rd floor. Zone 4. Slab formwork in progress.
Azman HKL: 1st floor. TA1. Slab formwork & lift rebar in progress.
Raymond Chong. Y. F (HKL P. Manager): zone 5a casting today
Azman HKL: Tq. Noted bos.
Azman HKL: Ground floor. Lift wall rebar, column rebar in progress.
Azman HKL: Ground floor. TB2.
Azman HKL: Basement. TB3. Column rebar in progress.
Azman HKL: 3rd floor. TB2. Column rebar and slab formwork in progress.
Azman HKL: Basement. Zone 3b. Slab foundation rebar in progress.
Raymond Chong. Y. F (HKL P. Manager): casting today also
Azman HKL: Yes bos...👌
Azman HKL: 3rd floor, 5a, M&E Inspection in progress.
Azman HKL: Done inspection. 👌
Azman HKL: @Azman HKL ni minta org dcc kasih gantung dia
+60 16-837 8881: 👌🏻
+60 17-866 0355: Gantung di kayu. Ko share la di group. 😅