Azman HKL: Good morning.
Site progress picture.
2/06/2023
Ground floor. Zone 7. Slab cast.
Azman HKL: Ground floor. Zone TB2. Slab cast.
Azman HKL: 3rd floor. Zone 5. Slab top rebar & flat slab formwork in progress.
Azman HKL: 3rd floor. Zone 5. Bottom rebar in progress.
Azman HKL: 3rd floor. Zone 4. Slab formwork in progress.
Azman HKL: 3rd floor. Zone TB1. Slab formwork in progress.
Azman HKL: 1st floor. Zone 2. Slab formwork in progress. Ground floor lift formwork in progress.
Azman HKL: Basement. Zone TB4&5 foundation in progress.
Azman HKL: Ground floor. Upvc pipe at high level in progress
Kadapi J. PROMES: Check kalau bata full height. Klu full height itu pipe mesti taru pipe sleeve. Tq
Kadapi J. PROMES: Saya sdh kasi tau c Roger tadi.
Kadapi J. PROMES: Econmech and KH, please check if any pipe sleeve near column area. If any u have to install it b 4 the bar installation start. FYI the bar at the column header is too narrow and its imposible for u to install pipe sleeve if the bar done 1st. Tq
Kadapi J. PROMES: Bossku Azman, tolong chek klu ada point d tiang. Ground Floor G-I/2-5.
Azman HKL: Jap
+60 12-843 3877: Sudah cek
Tiada point