Azman HKL: @~DartWeirdo 🇲🇾 @~Walker Yapi no one doing the opening & conduit? Very urgent. Slab cleaning on going. Push ini hari pagi kasi siap. 🙏🙏🙏
Azman HKL: @Leung KH🍀 tolong cek balik itu pipe sleeve.
Azman HKL: @Kadapi J. PROMES bossku. Request inspection 9.30am. Ground floor slab. Zone 7.
Azman HKL: @~YoonYK @+60 10-219 8082 hi morning. Request inspection with consultant the escalator pit at ground floor. This 1pm.
+60 19-821 8251: Ok noted.
Azman HKL: Escalator pit inspection with Mitsubishi done. 👌
NSC GROUP
Azman HKL: Morning.
Site progress picture. 1.06.2023.
Ground floor. Zone 7. Slab cleaning in progress.
Azman HKL: 3rd floor. Slab formwork & beam rebar in progress.
Azman HKL: 3rd floor. Zone 5. Slab rebar and formwork in progress.
Azman HKL: 3rd floor. Zone 4. Slab formwrok in progress.
Azman HKL: 3rd floor. Zone TB1. Slab formwork in progress.
Azman HKL: Ground floor. Zone TB2. Slab rebar and M&E in progress
Azman HKL: Basement. TB3. Column rebar in progress. TB4. Earthwork in progress
+60 14-331 3232: Minta maaf semua..ground floor sini mau minta kamu pinda barang kamu lagi..bata ada ubah..terima kasih semua🙏🏻
Azman HKL: M&E inspection in progress.
+60 17-866 0355: Ok bos
Azman HKL: Escalator pit inspection done. Some tolerance to adjust. 👌
Azman HKL: Ground floor zone 7. M&E inspection. Minor comment to rectify before cast.
Azman HKL: Ground floor. TB2. Done M&E inspection