 Azman HKL: Good Morning π.
Site progress picture. 
1/07/2023.
4th floor. Zone 5a. Bottom slab rebar work  in progress. M&E in progress.
Azman HKL: NSC PIC please submit your complete RFI form when work ready for inspection so I can arrange inspection with consultant on site. πππ. Double check all services before submitting.
NSC GROUP
Azman HKL: Good Morning π.
Site progress picture. 
1/07/2023.
4th floor. Zone 5a. Bottom slab rebar work  in progress. M&E in progress.
 Azman HKL: 4th floor. zone 4. Slab formwork in progress.
Azman HKL: 4th floor. Zone 5b. Slab formwork & rebar in progress.
 Azman HKL: 4th floor. Zone TB1. Slab formwork in progress.
Azman HKL: 1st floor. Lift wall formwork in progress.
Azman HKL: Basement. 8a. 7b.
Azman HKL: Basement. 8b.
Azman HKL: Basement. 3c.
Azman HKL: 1st floor. TA1. lift wall formwork in progress.
Azman HKL: Basement. 3a. Retaining wall rebar in progress. Target 1st cast by today.
Azman HKL: 4th floor. 5a. Bottom bar in progress then can run conduit on rebar. πͺ
Azman HKL: DCC on site.
 Azman HKL: Hujann...π§️
Azman HKL: Cast plan on monday.. π