Saturday, May 27, 2023

27 MAY 23 HKL

SITE GROUP

 Kadapi J. PROMES: Aku cuti ni hari🙂



NSC GROUP

 Azman HKL: Good morning. 
Site progress picture.
27/05/2023.
6th floor.
Azman HKL: 2nd floor. TB1. Slab cast.
Azman HKL: Ground floor. Zone 7. Slab formwork, beam & slab rebar in progress.
 Raymond Chong. Y. F (HKL P. Manager): Cast on 29/05/23
Raymond Chong. Y. F (HKL P. Manager): Please make necessary arrangements
Azman HKL: Please check the new layout from architect.

 Azman HKL: For the ground floor.

 Edwin Chen 013: Monday is 29/5/2023

+60 16-837 8881: 👌🏻

Azman HKL: Iya.. jari besar salah tekan bah.. 😅


Azman HKL: 3rd floor. Zone 4. Slab formwork in progress.
Azman HKL: 3rd floor. Zone 5. Slab formwork in progress.

 Azman HKL: Ground floor. Zone7. M&E in progress.