SITE GROUP
Kadapi J. PROMES: Aku cuti ni hari🙂
NSC GROUP
Azman HKL: Good morning.
Site progress picture.
27/05/2023.
6th floor.
Azman HKL: 2nd floor. TB1. Slab cast.
Azman HKL: Ground floor. Zone 7. Slab formwork, beam & slab rebar in progress.
Raymond Chong. Y. F (HKL P. Manager): Cast on 29/05/23
Raymond Chong. Y. F (HKL P. Manager): Please make necessary arrangements
Azman HKL: Please check the new layout from architect.
Azman HKL: For the ground floor.
Edwin Chen 013: Monday is 29/5/2023
+60 16-837 8881: 👌🏻
Azman HKL: Iya.. jari besar salah tekan bah.. 😅
Azman HKL: 3rd floor. Zone 4. Slab formwork in progress.
Azman HKL: 3rd floor. Zone 5. Slab formwork in progress.
Azman HKL: Ground floor. Zone7. M&E in progress.