Kadapi J. PROMES: Guys, aku cuti ni hari. Kurang sihat ku ehh๐ฐ
Azman HKL: Okay. Get well soon..
+60 12-833 6147: Take care bro..
Azman HKL: Site picture progress.
18/05/2023.
6th floor
Azman HKL: 2nd floor. Zone 5. Column rebar in progress.
Azman HKL: 2nd floor. Zone 4. Slab cast.
Azman HKL: 2nd floor. TB1. Slab formwork in progress.
Azman HKL: Basement, 7B. Support scaffolding for ground floor beam in progress.
Azman HKL: Basement. 7C. Slab Foundation rebar in progress. Earthing cable in progress.
Azman HKL: Basement. Foundation in progress.
Azman HKL: Ground floor. Slab formwork and beam rebar in progress.
Azman HKL: Basement. 5a. Beam support for ground floor in progress.
NSC GROUP
Azman HKL: @~Leppong @Leung KH๐ @~Walker Yapi please share some of your picture activity.๐๐
Azman HKL: @~Walker Yapi please check your duct level at basement. Especially that have cross with a sanitary pipe. ๐๐
Azman HKL: CIDB on site now. Please make sure safety work.
Lo. W. H (HKL-Site Engineer): Dear valued NSC, this is 4th floor flat slab