Wednesday, May 17, 2023

18 MAY 23 HKL

SITE GROUP

Kadapi J. PROMES: Guys, aku cuti ni hari. Kurang sihat ku ehh๐Ÿ˜ฐ
 Azman HKL: Okay. Get well soon..
+60 12-833 6147: Take care bro..
Azman HKL: Site picture progress. 
18/05/2023.
6th floor
Azman HKL: 2nd floor. Zone 5. Column rebar in progress.
 Azman HKL: 2nd floor. Zone 4. Slab cast.
Azman HKL: 2nd floor. TB1. Slab formwork in progress.
 Azman HKL: Basement, 7B. Support scaffolding for ground floor beam in progress.
Azman HKL: Basement. 7C. Slab Foundation rebar in progress. Earthing cable in progress.
Azman HKL: Basement. Foundation in progress.
 Azman HKL: Ground floor. Slab formwork and beam rebar in progress.
 Azman HKL: Basement. 5a. Beam support for ground floor in progress.


NSC GROUP
 Azman HKL: @~Leppong @Leung KH๐Ÿ€ @~Walker Yapi please share some of your picture activity.๐Ÿ™๐Ÿ™
Azman HKL: @~Walker Yapi  please check your duct level at basement. Especially that have cross with a sanitary pipe. ๐Ÿ™๐Ÿ™

Azman HKL: CIDB on site now. Please make sure safety work.




 Lo. W. H (HKL-Site Engineer): Dear valued NSC, this is 4th floor flat slab






















 