Azman HKL: New casting plan.
+60 17-866 0355: LV 1
Azman HKL: 2nd floor casting plan.
Azman HKL: Site progress. 6/05/23
6th floor. All column cast.
Azman HKL: 2nd floor. Zone 5. Slab formwork and bottom rebar in progress. Conduit work in progress.
Azman HKL: 1st floor. Zone TB1. Beam rebar in progress.
Azman HKL: Basement, zone 7B&7C. Foundation rebar in progress.
Azman HKL: Basement. Zone 5a. Retaining wall cast. Lift formwork in progress. Slab rebar in progress.
Azman HKL: 2nd floor. Zone 4. Slab formwork in progress.
Azman HKL: Ground floor, zone TA1. Slab& rebar formwork in progress.
Azman HKL: Basement. Lift wall rebar in progress.
Azman HKL: @Leung KHπ please check your pipe sleeve at 2nd floor. Kenapa semua tu tercabut?
Azman HKL: Basement. Tatai in progress..
Azman HKL: @EG Mall DCC Sshawnstchia @~. this area, 1st floor, TA1 casting plan tomorrow 7/5/23. Subcon target to complete the bottom rebar by 4pm for M&E. Please plan so that we can inspect and cast by tomorrow. ππ.
+60 16-837 8881: I try my best , tmr cast but today i cant start my work ......
Azman HKL: TQ.. π«°as we discuss. Depend on site conditions also.
+60 16-837 8881: Noted
Lo. W. H (HKL-Site Engineer): Dear all, this shall be the new design layout for 3rd floor which incorporated flat slab design
Lo. W. H (HKL-Site Engineer): please study and super impose your services drawing........ should there any services clash with the structure element ...you have to make way for structure..
Lo. W. H (HKL-Site Engineer): @~DartWeirdo π²πΎ especially your services
Azman HKL: 2nd floor. Zone 5. Conduit runs at the slab in progress.
Azman HKL: 1st floor. TA1. Beam rebar in porgress.
Azman HKL: Basement zone 5a.
Azman HKL: Basement. 7B
+60 12-843 3877: Slab 1st floor
Azman HKL: 1st floor. New casting plan on Monday. @~ShawnChia @~. please plan accordingly. Make sure ready on Monday.
+60 16-837 8881: Noted
Lo. W. H (HKL-Site Engineer): @~DartWeirdo π²πΎ Boleh jumpa besok pagi 8?
+60 16-801 0751: Tmorrow bole. But not 8 bos ππΏ. I will looking for u after ππΏ
Lo. W. H (HKL-Site Engineer): Thanks