Friday, April 28, 2023

29 APR 23 HKL

SITE GROUP
+60 14-379 2990: @Azman HKL just proceed yaa.. ECM tiada item area sini
 Leung KHπŸ€: KH Pipe Sleeve done
Kadapi J. PROMES: Only can proceed for official inspection after the rebar done.
Azman HKL: @Kadapi J. PROMES request for inspection. Tomorrow 9.30am. Ground floor slab. D-F/10-11. πŸ™

NSC GROUP
 Azman HKL: @~Walker Yapi @~DartWeirdo πŸ‡²πŸ‡Ύ ground floor sacffolding slab in progress. Please double check and coordinate to make sure your equipment can be placed in the room as we discuss. πŸ™πŸ™πŸ€²πŸ»
Azman HKL: Good morning. 
Progress picture report. 29/04/2023.
2nd floor slab formwork and beam rebar in progress.
Azman HKL: 2nd floor. Zone 4. Slab formwork.
 Azman HKL: Basement zone 2. Beam and slab for ground floor support scaffolding in progress.
 Azman HKL: Ramp 3. Column rebar & lighting conduit in progress.
 Azman HKL: Basement zon 5a. Retaining wall rebar, column rebar, lift pit wall in progress.
Azman HKL: 1st floor, slab formwork and column rebar in progress.
Azman HKL: Basement brick wall in progress
Azman HKL: Staircase 7
Azman HKL: Transformer room.
 +60 14-331 3232: Siapa punya barang d ground floor..tolong kasi pinda..sy mau setting bata..tq
Azman HKL: @~Walker Yapi πŸ‘†πŸ™πŸ™πŸ™
 +60 14-379 2990: Ok.. Boleh Mana area yg free boleh sy simpan ni barang? @Azman HKL
Azman HKL: @~YoonYK you want to come check after all that lift formwork done? Office n hotel lift pit.
+60 19-821 8251: Sure, will check on tuesday. πŸ‘Œ
 Azman HKL: Bomba lift pit at the supermarket area.
 +60 14-331 3232: Sini ko boleh simpan
+60 14-331 3232: Ground floor start setting brick layer suda
Raymond Chong. Y. F (HKL P. Manager): @~YoonYK every how many floors will u be checking the lift core wall verticality?
 Raymond Chong. Y. F (HKL P. Manager): 3 or 4?
 +60 19-821 8251: Currently we unable to check the verticality, only the lift shaft dimension as verticality check we need to conduct from the top floor.
Azman HKL: Casting plan besok?
Azman HKL: Casting plan bsok. Tolong check on site. @~Walker Yapi @~. @Leung KHπŸ€ .
 Azman HKL: @~ShawnChia  cuba tgk boleh siap pasang paip bsok ka?
 Raymond Chong. Y. F (HKL P. Manager): Ok
 Azman HKL: Bottom rebar in progress..
Leung KHπŸ€: Done
Azman HKL: Tolong post sana coordination bah. Ada consultant. πŸ™
 Azman HKL: @~ShawnChia subcon will make bottom bar ready at 3pm. Please arrange.. πŸ™
Azman HKL: @~Leppong @~. tolong take note.πŸ™.. please.....
 +60 17-866 0355: Ok man
Azman HKL: Please submit RFI. πŸ™
 +60 12-843 3877: Ribar in proggrass
 +60 12-843 3877: Installation pvc conduit for ELE/LV in prog@gfl
+60 12-843 3877: Instalation pvc conduit @gfl done

















































 

No comments:

Post a Comment

EGMALL NSC (23 SEPT 2024)

  EGMALL NSC (23 SEPT 2024) [23/9/2024 9:24 AM] EG MALL Mr Lo: @HIDAYA KH office Num ft ya Sini thanks [23/9/2024 9:24 AM] EG MALL Mr Lo: ...