Wednesday, April 26, 2023

27 APR 23 HKL

SITE GROUP
Azman HKL: Good morning.
Site progress. 27/04/2023.
1st floor. Formwork in progress.
 Azman HKL: 2nd floor slab form work and beam rebar in progress. Ramp3 parafet wall in progress.
Azman HKL: 2nd floor slab. Zone 4. Formwork in progress
Azman HKL: Basement. Zone 5a. Retaining wall rebar , column rebar and lift pit formwork in progress.
Azman HKL: Basement. Conduit runs at the brick wall in progress.
Azman HKL: Plinth setting out at basement AHU room in progress.
 Azman HKL: Staircase 7. Bottom rebar.
Kadapi J. PROMES: The conduit no longer use anymore due to staircase issue. Have to find new way for the conduit. We will solve on site asap. Location Staircase 7.
+60 10-941 8970: OK about this issue we was already discussing with a DCC man power sir, about this conduits staircase 7















 