Tuesday, April 25, 2023

26 APR 23 HKL

SITE GROUP
Azman HKL: Site progress picture. 26/04/2023.
2nd floor. Beam rebar in progress. Ramp3 column rebar in progress.
 Azman HKL: 2nd floor. Zone 4. Slab formwork in progress.
 Azman HKL: 1st floor slab&beam formwork. Scaffolding inprogress
Azman HKL: Basement. Zone 7b&7c earthwork& foundation in progress
Azman HKL: Basement. Zone 2B . Column and lift rebar in progress.
 Azman HKL: Basement brick wall in progress.
Azman HKL: Electrical conduit at brick wall in progress

NSC GROUP
 Azman HKL: @Leung KH🍀 check you pipe sleeve level. We are using an aluminium frame. Please install or mark the pipe sleeve area at the wall. TQ🙏🙏














 