Sunday, April 16, 2023

17 APR 23 HKL

SITE GROUP

 Azman HKL: @Kadapi J. PROMES request inspection. Basement and ground floor. 9.30am. ๐Ÿ™
Azman HKL: Morning. Site progress.
17/04/2023.
6th floor.
Azman HKL: Ground floor. Zone 11. Cleaning in progress.
Azman HKL: Basement. Zone 2B/b. Slab rebar & cleaning in progress.
Azman HKL: 1st floor. Zone 4. Column rebar in progress.
 Azman HKL: 2nd floor. Slab formwork in progress. Ramp 3 slab formwork & rebar in progress.
Azman HKL: Basement zone 5a. Plinth formwork and wall rebar in progress.
 Azman HKL: @~. @~Walker Yapi @Leung KH๐Ÿ€ joint inspection at ground floor. Zone 11.๐Ÿ™

 Kadapi J. PROMES: New layout for open kiosk gl 7-8/e-f. Conduit not yet install.

 Kadapi J. PROMES: KH and DCC, please be informed that there's new open kiosk at GL 7-8/E-F. Which is there need water supply, slab opening for FT, FWS and SSO point. Tq

 Kadapi J. PROMES: Those points not yet install ya guys๐Ÿ™‚

 Kadapi J. PROMES: Your action much appreaciated๐Ÿ™‚. Tq

 +60 12-843 3877: Bukan tak mau buat 
Kami belum ada update drowing
So how
Buat saja kah
Azman HKL: Site inspection in progress.
 Azman HKL: Basement inspection.
 Azman HKL: Mitsubishi check on site. BL1 office bomba lift pit opening at basement.
Azman HKL: Done repair from consultant comment. ๐Ÿ‘Œ
 Kadapi J. PROMES: ๐Ÿ‘

NSC GROUP
Azman HKL: Brick wall runs at basement.
 Lo. W. H (HKL-Site Engineer): for the Level 3
Lo. W. H (HKL-Site Engineer): can provide floor opening at these fan room ?
Lo. W. H (HKL-Site Engineer): @~DartWeirdo ๐Ÿ‡ฒ๐Ÿ‡พ
 Lo. W. H (HKL-Site Engineer): thanks
 +60 16-801 0751: Ok  ba๐Ÿ™๐Ÿฟ























 