Azman HKL: @Kadapi J. PROMES request inspection. Basement and ground floor. 9.30am. ๐
Azman HKL: Morning. Site progress.
17/04/2023.
6th floor.
Azman HKL: Ground floor. Zone 11. Cleaning in progress.
Azman HKL: Basement. Zone 2B/b. Slab rebar & cleaning in progress.
Azman HKL: 1st floor. Zone 4. Column rebar in progress.
Azman HKL: 2nd floor. Slab formwork in progress. Ramp 3 slab formwork & rebar in progress.
Azman HKL: Basement zone 5a. Plinth formwork and wall rebar in progress.
Azman HKL: @~. @~Walker Yapi @Leung KH๐ joint inspection at ground floor. Zone 11.๐
Kadapi J. PROMES: New layout for open kiosk gl 7-8/e-f. Conduit not yet install.
Kadapi J. PROMES: KH and DCC, please be informed that there's new open kiosk at GL 7-8/E-F. Which is there need water supply, slab opening for FT, FWS and SSO point. Tq
Kadapi J. PROMES: Those points not yet install ya guys๐
Kadapi J. PROMES: Your action much appreaciated๐. Tq
+60 12-843 3877: Bukan tak mau buat
Kami belum ada update drowing
So how
Buat saja kah
Azman HKL: Site inspection in progress.
Azman HKL: Basement inspection.
Azman HKL: Mitsubishi check on site. BL1 office bomba lift pit opening at basement.
Azman HKL: Done repair from consultant comment. ๐
Kadapi J. PROMES: ๐