Friday, April 14, 2023

15 APR 23 HKL

SITE GROUP
Azman HKL: Good morning .
15/04/23. Site picture progress.
6th floor.
 Azman HKL: Basement. Zone 5a. Cast.
 Azman HKL: Basement. Zone 2B/b. Rebar work in progress.
Azman HKL: 1st floor. Zone 4. Column rebar in progress.
Azman HKL: 2nd floor. Zone 3. Slab formwork in progress. Ramp 3 rebar in progress.
Azman HKL: Ground floor. Zone 11. Slab rebar in progress.
Azman HKL: @Leung KH๐Ÿ€ check any floor trap here. TQ.๐Ÿ™
Leung KH๐Ÿ€: Yes got floor trap there as we discussed yesterday ๐Ÿ™๐Ÿป


NSC GROUP
Raymond Chong. Y. F (HKL P. Manager): Ground Floor Zone 11 bottom bars completed, please arrange to fix M&E conseal, thank you


 Azman HKL: DCC runs conduit at slab rebar in progress.
Azman HKL: King Hong on site setting out the pipe sleeve at the slab.
Azman HKL: @~. @Leung KH๐Ÿ€ @~Walker Yapi pls share some pic progress to the group. ๐Ÿ™๐Ÿ™๐Ÿ™..
 Leung KH๐Ÿ€: Done

 
Azman HKL: Zone 2a wall formwork in progress and columns I/1






















 