Azman HKL: Good morning .
15/04/23. Site picture progress.
6th floor.
Azman HKL: Basement. Zone 5a. Cast.
Azman HKL: Basement. Zone 2B/b. Rebar work in progress.
Azman HKL: 1st floor. Zone 4. Column rebar in progress.
Azman HKL: 2nd floor. Zone 3. Slab formwork in progress. Ramp 3 rebar in progress.
Azman HKL: Ground floor. Zone 11. Slab rebar in progress.
Azman HKL: @Leung KH๐ check any floor trap here. TQ.๐
Leung KH๐: Yes got floor trap there as we discussed yesterday ๐๐ป
NSC GROUP
Raymond Chong. Y. F (HKL P. Manager): Ground Floor Zone 11 bottom bars completed, please arrange to fix M&E conseal, thank you
Azman HKL: DCC runs conduit at slab rebar in progress.
Azman HKL: King Hong on site setting out the pipe sleeve at the slab.
Azman HKL: @~. @Leung KH๐ @~Walker Yapi pls share some pic progress to the group. ๐๐๐..
Leung KH๐: Done
Azman HKL: Zone 2a wall formwork in progress and columns I/1