Azman HKL: Good morning.
6/4/23. Site progress
Zone 4. Slab rebar and M&E services in progress.
Azman HKL: Basement. Zone 2B. Foundation slab rebar in progress. Column rebar in progress.
Azman HKL: 2nd floor. Zone 3a. Beam formwork in progress. Ramp 3 formwork in progress.
Azman HKL: 6th floor. Column closure in progress.
Azman HKL: Basement zone 2B.
+60 14-331 3232: @Azman HKL morning broππ»♂️boleh suru org ko kasi pinda lari in saja..tq
+60 14-331 3232: Basement
Azman HKL: @Leung KHπ boleh tolong atur? Archi maw setting bata sana.πππ
Azman HKL: @EG Mall DC Raman @EG Mall Plumber Leung WK - King Hong @EG Mall Econmech Walkeryapp Yapi We target M&E RFI at 3pm. Tolong usahakan sampai jaya.πͺ. Kalau lagi awal lagi baik. Kalau ada masalah tolong share kita boleh bincang kasi selesai...
+60 12-843 3877: Saya sudah kan?
Edwin Chen 013: Are you starting to do the wall for the pump ejector room?
Azman HKL: the brick will begin to install. Starting basement watertank area. But the ejector room and any M&E room with equipment will stay open on the front wall to insert equipment. if there is a problem please assist.
+60 14-331 3232: Scaffolding suda buka..tolong atur
Azman HKL: @~Calvin ko tgk ok sda ba kan..
+60 14-331 3232: Gitu ok suda
+60 14-331 3232: π€
Azman HKL: M&E inspection in progress. 1st floor. Zone 4.
+60 14-331 3232: Ini kena juga..mau pinda juga..ada bata sini juga..tqππ»
+60 14-331 3232: Ini mau pinda juga
+60 14-331 3232: Ini semua d dalam staircase kena juga..ada bata jalan sini juga..tqππ»
+60 12-843 3877: M&E inspection in progress. 1st floor. Zone 4.
+60 12-843 3877: Ele/Elv allready insfection
Azman HKL: M&E inspection done..π
Azman HKL: Basement. AHU room slab. Casting plan on this Saturday. @Leung KHπ
@~ShawnChia @~Walker Yapp please take note.
+60 16-837 8881: Noted
Raymond Chong. Y. F (HKL P. Manager): This been postponed to next Monday
Azman HKL: Noted bos.. ππ»