NSC GROUP
Azman HKL: Good morning.
5/4/23. Site progress picture. 1st floor. Zone 4. Rebar and M&E services at the slab in progress.
Azman HKL: Basement. Zone 5A. Basement foundation in progress.
Azman HKL: Basement. Zone 2B slab in progress.
Azman HKL: Ground floor. Zone 11. beam and slab formwork in progress.
Azman HKL: 2nd floor. Beam formwork in progress.
Azman HKL: 1st floor. Zone 3B. Column rebar in progress.
Azman HKL: Installing bottom reinforcement bar zone 2Ba