Monday, April 3, 2023

04 APR 23 HKL

SITE GROUP

Azman HKL: Good morning. 4/4/23. 
Site picture progress. 
1st floor. Zone 4. Slab rebar in progress.
Azman HKL: 1st floor. Ramp 3. Formwork in progress.
 Azman HKL: 2nd floor. Beam formwork in progress.
Azman HKL: 1st floor. Zone 3b. Column rebar in progress.
 Azman HKL: Basement zone 7a. Column rebar in progress.
Azman HKL: D / 9
 Azman HKL: @⁨EG Mall Demi Cerah Eddy Dcc 017⁩ construction drawing. PC18/21/ES/ML/04. Mall 2nd floor plan it shows for ELV & elec riser room. Please double check with your drawing. 👆
+60 17-866 0355: Ok man tq
Azman HKL: @~Liaw Ka Pang @~Lawrence Yapp @~DartWeirdo 🇲🇾 @Edwin Chen 013 As instructed by Client, I have send an emailed to you a letter from ABLT. 

Amendments:
1. Two escalators relocated. Also the open kiosk.
2. Revised toilet layout at Hotel Lobby.
Please check and study the new drawing. Any problem please highlight as soon as possible. Thanks.

NSC GROUP
Azman HKL: King Hong team on site install pipe sleeve..
Azman HKL: Econmech Super Visor on site..

Azman HKL: Raining..🌧️



















 