Azman HKL: 1st floor. Scaffolding support for 2nd floor beam in progress.
Azman HKL: 1st floor column rebar in progress.
Azman HKL: Ramp 3. Slab formwork in progress.
Azman HKL: GL: L/8-11. Earthwork in progress.
Azman HKL: Zone 7a. Column rebar in progress.
Azman HKL: 3/04/2023.
Good morning. Site picture progress.
Zone 4. Beam rebar in progress.
Azman HKL: Basement. GL: I-L/11-14. Basement foundation lean con in progress.
Azman HKL: @Leung KH๐ we found that pipe was damage during backfilling. please check and do what is necessary. we try to prevent accidents like this from happening.๐
Azman HKL: Maybe we need marking so in future Hitachi drivers will alert that there is a pipe below.
Azman HKL: 6th floor column in progress..
Azman HKL: Iya.. belum ada bottom bar. Sedang atur.. ๐คฒ๐ป๐ช๐ช๐ช
Azman HKL: Zone 4. Slab bottom rebar in progress.
+60 12-843 3877: ๐ช
Raymond Chong. Y. F (HKL P. Manager): 1st floor Zone 4 slab casting postponed to Thursday
Azman HKL: Please take note all NSC. This zone's target cast is on. 6/4/2023. @E@~ShawnChia @~. @~Leppong @~DartWeirdo ๐ฒ๐พ @~Walker Yapp @Leung KH๐ please check and plan. Any obstruction inform early. Tq.
+60 16-837 8881: ๐๐ป